5 Schedule

Development schedule for lOOOkW pilot plant is shown in Fig. 4.

In November 1996, the building work of the Kawagoe site will be finished. The plant equipments fabrication will be finished in FY 1996, and they will be installed and adjusted in FY1997. The PAC test will be carried out in FY 1998. And the operation will be carried out in FY 1999. At present, every equipment are being fabricated by makers. And the Kawagoe MCFC test center is preparing for the equipment installation and PAC test. The recent photo of the Kawagoe site is shown in Fig. 5.

Fiscal Year

0 0